Work to Start
Next Week on
Adler Drive-In
The necessary permits to proceed
with the construction of the new
outdoor theater south of the city
have been received and work will
begin Monday, it was announced to-
day by J.P. Adler, president of the
Adler Theater Co. Inc.
The Eau Claire Nursery Co. will
undertake the first portion of the
job, that of grading the site. The
construction of the screen and the
wiring of the premises, plus the
construction of the projection house
and concession stand is expected
to take about six to eight weeks.
With a break from the weather-
man, Adler said he hoped to have
the new theater operating by the
second week of September.
A 37 by 50 screen, elevated some
50 feet in the air, will face north-
east. The entrance will be on high-
way 10, about 1200 feet east of the
intersection with highway 13. The
exit will be 800 feet north of the in-
tersection on highway 13. There
will be facilities for 425 cars.